Breaking concrete<\/a> in all lanes to prepare for repaving along the four-mile section.<\/p>\n• Paving nearly 3,000 dump truck loads of asphalt – approximately 43,000 tons of pavement.<\/p>\n
• Replacing 88 broken concrete panels near SR 516.<\/p>\n
“Our contractor crews have accomplished a lot, even though one weekend they had to stop working for half a day because of rain,” WSDOT Project Engineer Mike Askarian said. “We are on schedule to complete the paving in mid-August, and we’ll be able to finish all the paving and striping in this section before winter.”<\/p>\n
More weekend paving<\/strong><\/p>\nTo finish the second half of the paving, three more weekends are scheduled when northbound I-5 will be reduced to two lanes between SR 516 and South 170th Street:<\/p>\n
• July 7-10 and 14-17<\/p>\n
• Aug. 11-14<\/p>\n
• Lanes will begin closing at 8 p.m. each Friday and reopen by 5 a.m. each Monday.<\/p>\n
• The work is weather-dependent and could be postponed by rain<\/p>\n
Additional lane reductions for expansion joints<\/strong><\/p>\nWhen paving is complete, work will shift to replace expansion joints and repair the bridge decks of the Interurban Avenue overpass and the Duwamish River Bridge above I-5. This will require two weekend-long lane reductions in later this summer or fall, and two more in the first half of 2018.<\/p>\n
Concrete panel replacement and other work will continue during weeknight lane reductions, which will last until the project is complete in summer 2018.<\/p>\n
Reviving I-5<\/strong><\/p>\nBy next summer, northbound I-5 between South 260th Street in Kent and the Duwamish River will have about 440 new panels, four miles of new asphalt pavement, and eight new expansion joints at Interurban Avenue and the Duwamish River. Additionally, concrete grinding will eliminate ruts on five miles of the highway. When finished, the pavement on this stretch of I-5 will last longer and travelers will have a much smoother ride.<\/p>\n","protected":false},"excerpt":{"rendered":"
Crews break for Independence Day, weekend work resumes July 7 <\/p>\n","protected":false},"author":106,"featured_media":29139,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[9,4],"tags":[],"yst_prominent_words":[],"class_list":["post-29137","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-home","category-news"],"_links":{"self":[{"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/posts\/29137"}],"collection":[{"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/users\/106"}],"replies":[{"embeddable":true,"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/comments?post=29137"}],"version-history":[{"count":0,"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/posts\/29137\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/media\/29139"}],"wp:attachment":[{"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/media?parent=29137"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/categories?post=29137"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/tags?post=29137"},{"taxonomy":"yst_prominent_words","embeddable":true,"href":"https:\/\/www.kentreporter.com\/wp-json\/wp\/v2\/yst_prominent_words?post=29137"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}