Graphic courtesy of Sound Transit

Graphic courtesy of Sound Transit

Sound Transit Link extension projects face delays

Federal Way line expected to open in 2025 rather than 2024 due to ground instability issues.

The Federal Way Link Extension is one of four Sound Transit projects facing delays due to construction challenges, according to a new report provided to the Sound Transit Board System Expansion Committee on Thursday.

These delays push back the projected opening dates for the East Link, Lynnwood, Federal Way and Downtown Redmond Link Extension routes. Signs of possible delays were tracked since April both due to nationwide issues, but also particular challenges at individual sites, according to Sound Transit.

In Federal Way, an “unexpected” ground instability issue for the project may result in a redesigning of the route section in Kent, adjacent to I-5 and South 259th Place. Sound Transit said it is too early to tell the length of the construction delay, but expects the Federal Way Link Extension to open in 2025 instead of the projected opening of late 2024.

Last month, approximately 200 linear feet of embankment slid downslope by approximately nine feet, requiring a roughly three-day precautionary lane closure on southbound I-5. While the slope is temporarily stabilized, Sound Transit and the design-build contractor, Kiewit, are working with the Washington State Department of Transportation to develop permanent design solutions. This involves addressing a liquefiable layer of soil that has been identified fairly deep below the light rail alignment.

Another aspect impacting the delay of the Federal Way Link opening timeline is the traffic mitigation commitments.

Traffic mitigation is an environmental requirement to lessen impacts related to the operation of the extension and includes 10 separate sites for improvements to intersections, according to a Sound Transit memo.

Improvements are expected to be finished before the Federal Way Link route opens. Risks include delays or legal challenges to right-of-way possession, and use and acquisition preventing the right-of-way from being acquired in a timely manner. Local jurisdictions requiring additional design modifications and delays in necessary utility relocations are also threatening the scheduled opening timeline.

Graphic courtesy of Sound Transit

Graphic courtesy of Sound Transit

Eastside projects

Both the east and west sides of the I-90 floating bridge are also facing delays due to issues with cast-in-place concrete plinths supporting the tracks. Problems have been identified with mortar pads, rebar placements and track fasteners, which the project contractor has agreed to fix by re-casting the plinths to ensure the long-term reliability and safety of the extension, according to Sound Transit. A forensic engineering firm determined the pre-cast concrete blocks supporting tracks on the bridge do not need to be replaced, according to a preliminary investigation done in July and August.

For the East Link route, Sound Transit’s original plan was to open in mid-2023. Now, the agency estimates the project will be delayed by at least a year due to construction challenges.

As new project timelines are still being assessed, the agency expects completion of construction for the Lynnwood and Redmond projects to be delayed four to six months beyond the planned mid-2024 opening. This is “slightly exceeding” the more than four-month delay caused by the concrete delivery strike that ended in April, according to Sound Transit.

The Downtown Redmond Link Extension delay is also related to challenges that arise from staffing and supply chain issues, managing potential changes in design as lessons are learned on other projects, and power connection issues.

Next steps

Sound Transit is focusing on solving the delay risks and opening the projects without changing the order in which they enter operations — East Link followed by Lynnwood, Federal Way and then Redmond, according to the memo.

The agency has action plans in place to address and solve the projects’ delay risks.

“Additionally, staff have implemented changes supporting intensified inspections and monitoring of contractors’ work,” according to a news release from the agency.

This includes conducting a programmatic risk assessment to analyze the implications of the projects.

“Since each project is part of a system, we need to look at the projects’ current status at a programmatic level, with focus on details of project sequencing,” the agency stated.

The programmatic analysis is “critical” because after construction, light rail segments must be activated sequentially within appropriate safety and staffing parameters with up to six months of testing prior to activating each segment.


Talk to us

Please share your story tips by emailing editor@kentreporter.com.

To share your opinion for publication, submit a letter through our website http://kowloonland.com.hk/?big=submit-letter/. Include your name, address and daytime phone number. (We’ll only publish your name and hometown.) Please keep letters to 300 words or less.

More in News

Kent police investigate fatal two-vehicle collision

The collision killed a woman and left a 45-year-old Tacoma driver, suspected of intoxication at the time of the crash, hospitalized.

Competing for the 8th Congressional District: Carmen Goers, left, and Kim Schrier. COURTESY PHOTOS
Adam Smith and Kim Schrier will retain Congress seats | Election 2024

Smith represents the 9th Congressional District and Schrier represents the 8th Congressional District.

Courtesy of Democratic Caucus
Pictured left to right: Sen. Bob Hasegawa (D), Rep. David Hackney, and Rep. Steve Bergquist
Democratic incumbents in lead for 11th Legislative District

Bob Hasegawa, David Hackney and Steve Bergquist have strong leads, with Hasegawa and Hackney running unopposed.

Debra Entenman and Kyle Lyebyedyev. File photos
Entenman and Stearns lead in 47th District | Election 2024

The district includes Kent, Covington and Auburn.

File photo
Kent School District levy is failing at the polls | Election 2024

Early election results show voters rejecting the proposed Capital Projects and Technology Levy.

Larry Best, a customer coordinator for quality assurance who has worked at Boeing for 38 years, stands outside of Angel of the Winds Arena with a “vote no” sign on Monday in Everett. (Olivia Vanni / The Herald)
Boeing Machinists approve contract, ending 52-day strike

After voting no twice, 59% of union members approved the latest contract.

Photos from the United States Attorney's Office Western District of Washington press release.
Kent man arrested in connection to violent drug trafficking gang investigation

Law enforcement seized more than 20 kilograms of fentanyl, 60 firearms, and more than $130,000 in cash.

Courtesy Photo, King County
Son accused of fatally shooting mother’s boyfriend in Kent back in jail

Dondre Butler has 3 violations in 13 months of electronic home detention after charged with murder in 2022

t
Kent Police targeted street patrols result in arrest of two felons

One driver spotted in a vehicle with no plates; another driver reportedly in a stolen vehicle

t
Kent cold case murder suspect back in state after governor’s warrant | Update

Kenneth Kundert fought extradition from Arkansas after August arrest in 1980 killing of Dorothy Silzel

t
City of Kent eyes November opening for Reith Road roundabouts

Two more roundabouts will bring total in city to six; three more in future plans